CFECapital, the investment division of Mexican state-owned electric utility CFE, is planning to raise around $2.8 billion in the next few years to finance new projects, a CFE spokesperson told LatinFinance.
The fundraising plans could “be structured through different instruments, whether capital and/or debt issuances, depending on investment needs, financial strategy and market conditions,” the person said.
“No single issuance is expected to reach [$2.8 billion], but rather a combination of alternatives will be evaluated over the next few years,” the spokesperson said.
One alternative under consideration is a follow-on offering by CFE’s energy and infrastructure investment trust, CFE Fibra E.
It would the Fibra’s first such transaction since its IPO in 2018, the company said in a press release on Wednesday. CFE raised MXN16.4 billion (then $868 million) in the initial share listing.
“CFECapital will continue to evaluate market conditions to identify the most favorable potential moment for” the follow-on, it said in the press release.
BOND MARKET
The proceeds from future fundraisings will be used by CFE to support projects tied to the Mexican government’s $28.2 billion plan to expand electricity generation, transmission, and distribution between 2025 and 2030, the spokesperson said.
Of this amount, about $8.5 billion is earmarked for transmission, including roughly $3.5 billion for projects tied to CFE Fibra E. Part of this funding has already been secured through a $725 million bond sale in September last year.
Any additional bond sales “will depend on market conditions and demand,” the spokesperson said.
POWER BOOST
The government’s investment program seeks to add 21,846 MW of new generation capacity. Of this, CFE will account for 15,446 MW through new generation projects and battery storage systems, while the private sector is expected to add 6,400 MW through clean energy developments, according to government data.
Additionally, ten power plant projects initiated under the previous administration are expected to come online between 2025 and 2030, and sixteen hydroelectric plants will be upgraded, adding a combined 6,717 MW.