Argentina’s Camuzzi Gas Inversora plans to raise $500 million in project financing for a a new floating liquefaction facility to export LNG, project head Daniel Ridelener told LatinFinance.

The company will start talks with banks this year and wrap up the financing next year, he said in an interview.

The goal is to have the deal in place for when it makes a final investment decision on the $4.1 billion project in the third quarter of next year, Ridelener added.

Camuzzi, a leading gas distributor in central and southern Argentina, first announced plans for the LNG del Plata project in December last year and went on to strike a pre-deal with Geneva-based commodities trader Vitol as the offtaker in April. Vitol will buy 100% of the output from the facility, guaranteeing future revenue—a key requirement for the financing.

Camuzzi will install the floating liquefaction terminal in the Río de la Plata estuary off the coast from Port of La Plata on the southern outskirts of Buenos Aires.

Ridelener said that once the final investment decision is taken, the project will take 30 months to complete. The operations are slated to start in the first half of 2030, he added.

LNG del Plata is the third LNG project under construction or in the pipeline in Argentina, helping to monetize the huge gas resources in Vaca Muerta, a shale deposit in northern Patagonia.

The three projects will have a total of 26.5 million metric tons per year of export capacity, allowing the country to capture 5% of the global LNG market, currently dominated by Australia, Qatar and the United States, Ridelener said Tuesday at an event in Buenos Aires hosted by the Argentina Oil and Gas Institute.

Argentina exports some 10 million cubic meters per day to neighboring countries via pipelines, but most of the growth will come from LNG shipped via the Atlantic.